Firing Luma Was the Easy Part

2026-11-28 · Washington Eye Team

A rebuilt transmission tower and power lines cut through hurricane damaged forest near Caguas, Puerto Rico, during grid restoration after Hurricane Maria (photo: US Army Corps of Engineers, South Atlantic Division, public domain, via Wikimedia Commons), edited for Washington Eye cover
WhatsAppX

On Black Friday, thousands of Puerto Ricans skipped the sales and marched instead. Retirees, university students and bus drivers gathered in San Juan in front of the largest shopping mall in the Caribbean for what some 30 organising groups, from labour unions to religious congregations, called a "Day of National Outrage." Their grievances ran from water cuts to the cost of groceries, but one complaint united the crowd: the electricity bill, and the lights that still go out after it is paid. It was one of the largest protests since Governor Jenniffer González Colón took office in January 2025.

Two days earlier, the governor had handed them what looked like a victory. On 25 November, Puerto Rico's Supreme Court ruled 5 to 4 that the extension of the arrangement under which Luma Energy runs the island's transmission and distribution grid was void. Luma, a company formed by subsidiaries of Canadian Utilities and Quanta Services, has operated the wires and poles since June 2021. The court ordered an orderly handover to a new operator within one year, supervised by a trial court.

Ending the Luma contract was the signature promise of the González campaign, and she has earned the right to celebrate. But the hardest truth for the people who marched on Friday is this: firing Luma was the easy part. Nothing in Wednesday's ruling, and nothing in the governor's plan so far, will by itself bring down the bill that drove them into the street. If Puerto Rico treats this moment as the end of a fight rather than the start of a much harder one, it will spend another year angry, and another decade in the dark.

Start with what the court actually decided. The majority opinion, written by Associate Justice Luis Estrella Martínez, found that a letter extending Luma's supplemental agreement substantially changed the terms the parties had originally signed. Changes of that size, the court said, had to clear the same safeguards as the original deal, including a yes vote from the two public interest members on the board of the island's Public Private Partnerships Authority and a compliance certificate from the Puerto Rico Energy Bureau. Neither happened. The court also found that the extension left some contract conditions to Luma's sole discretion, which the law forbids.

That is a ruling about process, and a damning one. A public contract worth billions was stretched without the approvals the law demands. The four dissenters, among them Chief Justice Maite Oronoz Rodríguez, saw it differently. Associate Justice Rafael Martínez Torres argued that the extension was valid, did not amount to a new transaction and deserved respect under freedom of contract. A one vote margin on a ruling of more than 200 pages is not the sound of a settled question. Luma's parent company said it plans to ask the court to reconsider and intends to pursue "all available rights and remedies."

The governor has framed the outcome as vindication. "Six to zero," she told reporters at La Fortaleza, counting her wins against the operator in court. "I have lost many polls, but never an election." She said there are companies interested in replacing Luma, "and after this decision there will be more," and promised a committee of energy experts to steer the transition. Grid operations, she has said, will not go back to the old public utility, the Puerto Rico Electric Power Authority, known as PREPA.

Her case against Luma is not imaginary. Islanders have lived with blackouts, voltage swings that fry appliances and repairs that drag on for years after Hurricane Maria flattened the grid in 2017. "The real cost of LUMA is that they solve everything by asking Puerto Rico for a rate increase," the governor said, "and today we have the most expensive electricity in the history of our island." Fuel prices and world events are one thing, she added; "mediocrity and a lack of operational diligence" are another.

She is right that the bill is historic. For October through December, the Energy Bureau set the residential rate at a record 33.86 cents per kilowatt hour, an increase of about 18 percent that adds $42.27 a month for an average unsubsidised household. Federal figures put the average residential price on the US mainland at 17.23 cents in 2025. Puerto Ricans are paying close to twice the mainland average for power that is far less reliable.

But read the regulator's own order and a different culprit comes into view. The largest moving part in the bill is not Luma's management fee. It is fuel. The quarterly fuel charge alone jumped from 11.41 cents to 17.36 cents per kilowatt hour, more than half of the entire residential rate. The Energy Bureau traced the rise to several causes: base generating units that remain out of service, forcing the system to burn more expensive ultra low sulphur diesel; shortfalls in natural gas deliveries that had to be replaced with diesel and heavy fuel oil; unplanned breakdowns at power plants; and fuel bills from the summer that came in higher than projected.

None of those power plants are run by Luma. Generation on the island is operated by a different private company, Genera PR, under a separate agreement. Natural gas arrives under contracts with a separate supplier, New Fortress Energy, whose disputes with the island the regulator specifically cited when it ordered a full audit of gas costs, deliveries and credits. Luma files the rate requests because it runs billing. That makes it the face of every increase. It does not make it the author of every cent.

The regulator was blunt about this. When it trimmed Luma's request, cutting the proposed fuel charge by roughly one cent and deferring $17.6 million tied to gas supply failures, it warned that saying no does not make the money vanish. "Not approving the fuel charge proposed by LUMA does not eliminate these costs," the order said. "The fuel already consumed has to be paid for."

So here is the uncomfortable arithmetic. A new grid operator, however competent, will inherit the same broken baseload plants, the same fuel contracts, the same diesel habit and the same bankrupt public utility. On day one of its tenure, the bill will look almost exactly like the bill that brought thousands of people to the mall on Friday.

Then there is the clock. The court gave Puerto Rico one year to find, hire and install a replacement. Specialists consulted by the island's largest newspaper warned this week that twelve months will not be enough for an orderly transition. The government must recruit bidders while the outgoing operator is fighting the ruling, and while the operator's workforce waits to learn who will employ it next year.

Puerto Rico's federal Financial Oversight and Management Board, created by Congress under the law known as PROMESA, has already sounded the alarm. Terminating the operator "without a clear plan or successor company in place," the board said, creates "enormous uncertainty" and risks setbacks in maintenance, in the deployment of federal disaster recovery funds and in PREPA's "already distressed finances." That last point matters more than it sounds. Billions of dollars in federal recovery money set aside after Maria flow through grid projects. Every month of confusion over who signs the work orders is a month those projects stall.

None of this is an argument for keeping Luma. The court has spoken, and the operator's own record gave the governor plenty of ammunition. It is an argument for honesty about what comes next. If the government sells the transition as relief for household budgets, it is setting itself up for a second, angrier Day of National Outrage a year from now.

What would a serious plan look like? First, the next operator's contract should be written in public, with performance targets that ordinary customers can check: outage minutes, restoration times, the share of federal projects completed on schedule, and real financial penalties when those targets are missed. The current mess grew partly from a contract that let the operator set some of its own conditions. That must not happen again.

Second, the government should put at least as much political energy into generation as into distribution. Getting the idle baseload units back online and fixing the natural gas supply would do more for the monthly bill than any change of logo on a service truck. The Energy Bureau's audit of gas costs should be finished quickly and published in full.

Third, Washington has a role it keeps ducking. More than three million American citizens live on the island. The federal government created the oversight board, controls the disaster money and has watched the grid limp along for nine years since Maria. Federal agencies should commit now to keeping recovery funds moving through the transition, so that the handover does not become another excuse for delay.

The marchers in San Juan were not wrong to be furious. They pay mainland prices twice over for power that fails them weekly. But anger aimed at a single company is an easier politics than the slow work of fixing power plants, fuel supply and a public utility that never recovered from bankruptcy. The governor won her case. The test of her promise is not whether Luma leaves. It is whether the bill, and the blackouts, finally start to fall after it does.